11/2012
to Present
Lockheed Martin Corporation
5/2012
to 11/2012
Disys Corporation (Subcontracted to Lockheed Martin) New
Orleans, LA
Senior
Engineer Planner
Develop, status, and analyze Master Integrated
Production Schedule (MIPS) in sufficient detail to monitor progress, assess
program status, and identify performance issue for the complex, multi-year,
multi-million dollar project aimed at upgrading US Navy Standard Integrated
Personnel System (NSIPS).
· Maintain several project schedules
to monitor progress of the software development life cycle. Ensure that
scope of work, activity sequencing, task duration, resource allocations and
multiple schedule interactions are presented with accuracy. Ensure program
milestones are completed in accordance with the contract requirements.
· Prepare schedules for weekly team
meeting where project leads are presented with work forecast, resource
allocation, and long term planning. Gather updates from project leads on a
weekly basis. Control schedules by monitoring & tracking the status of
projects using MS Project, resource loading, updating progress and managing
changes to the schedule baselines. Formulate and recommend corrective
action measures such as schedule revisions.
· Serve as point of contact between
the customer and project leads. Facilitate weekly meetings with the
customer to update project progress, schedule performance and documentation
status. Provide customer with monthly reports on MIPS progress.
· Support proposal activities in the
development of schedules for upcoming projects and ensure that resources
are available and efficiently allocated. Track the development of software
change and problem requests to ensure timely completion to meet production
release deadlines.
4/2008
to 12/2011
L-3
Westwood
Harahan, LA
Master
Scheduler
Developed and maintained the Integrated Master
Schedules (IMS) for the construction of the US Navy’s T-AGM 25 and upgrade
of T-AOE 6 Programs.
· Worked with program management and
engineering to ensure that the production schedule met customer and company
needs. Provided status of the IMS for monthly reporting. Ensured
management was aware of pending documentation necessary to meet upcoming
milestones or design reviews.
· Maintained several supporting
schedules for smaller scale existing projects. Analyzed schedules for
performance metrics including late and past due tasks. Reported schedule
baselines changes, percentage completion, schedule variances and resource
over allocations.
· Collected progress, update and
reported projects status. Worked closely with the project management team
to set project goals, coordinated schedule updates and analyzed the status
of the project. Analyzed schedules to determine duration and logic issues.
· Updated and produced scheduling
management reports for monthly program reviews, including look ahead
reports and EVMS analysis. Assembled data for schedule updates and assisted
in coordination of schedule inputs from all parts of the organization.
Analyzed schedule for resource needs and performed minimal schedule risk
analysis.
8/2006
to 4/2008
Northrop Grumman Ship Systems
Avondale, LA
Project
Schedule Coordinator
Coordinated
emergent and special projects as assigned to provide management with
information and statistical data necessary for decision-making in the
development of the US Navy’s LPD 18, LPD 20, and LPD 21.
· Developed charts, graphs and reports to provide analysis
on historical data comparing forecast v. actual dates to help determine
future trend estimations.
· Provided support in scheduling, tracking, and analysis
and project reporting. Maintained key production schedules for delivery and
assisted production and planning supervisors in updating and coordinating
schedules. Tracked schedule performance and monitored performance against
the baseline. Analyzed critical path network and schedules while ensuring compliance
with company's policies and procedures and schedule deadlines
· Re-dated and re-planed production schedules based on new
deadlines and schedule dates. Dated work authorizations based on company
specified criteria. Updated and maintained weekly progress of bill
completion and progress.
· Updated, maintained and monitored compartment completion
databases for LPD 20 and LPD 21. Assisted crafts in updating craft
completion information. Prepared weekly analysis reports based on the
database information.
· Received Training on OSHA
construction safety requirements. Under certain circumstances was required
to wear Personal Protection Equipment (PPE) when in construction areas.
2/2006 to 8/2006
Northrop Grumman Mission
Systems
New Orleans, LA
Configuration
Analyst
Provided assistance to
the Customer Technical Representative (CTR) to successfully meet government
obligations during the transition into the NMCI environment.
· Coordinated with site managers to
collect initial site data and assist in the completion of NMCI computer
ordering. Provided site administrative NMCI support services, created and
updated user profiles, user to application mapping, seat mapping, and building
to seat mappings.
|